Westwood Fire Company
Westwood
2010 Call Stats
  Fire EMS
Jan 18 55
Feb 14 47
Mar 17 52
Apr 22 63
May 17 48
Jun 33 49
Jul 0 0
Aug 0 0
Sep 0 0
Oct 0 0
Nov 0 0
Dec 0 0
Total 121 314

Past Call Stats
Year Fire EMS
2009 304 639
2008 314 707
2007 321 663
2006 316 727
2005 344 796
2004 349 742
2003 388 625
2002 389 707
2001 375 647

Visitors Today:
648

Visitors Since
September 16, 2005:
787,142

Building Construction Update
Email Print PDF RSS
By Building Committee
May 28, 2010
 
For the past several weeks, the addition to the fire station has been steadily moving along, despite the bad weather we have been having.

Our new building is a big movement for our Company. Our Building Committee was established in 2009 and consists of the following members:

Hower Smith, III - Chairman
Kathy Amer
John Sly
Mike McWilliams
Randy Scott

We intend to provide updates to the community on our website as this project progresses.

12/30/09:

After groundbreaking, the footers have been dug and filled with concrete. They have also started the block laying and are making good progress.

Within the next few weeks the outer base walls will be completed and work on removing the roof will start.

1/20/10:

The new bay frames are beginning to take shape as the block continues to be layed out. The new East wall of the firehouse is complete and the rear drive-through bays are beginning to see mason work.

2/3/10:

On the week of January 25th, the support beams were placed and the block work was nearly completed. We also had Vietri Electric in to shut off power to unneeded electrical outlets.

On the week of February 1st, crews from Vietri Electric, Simmers Builders, and Baldwin Heating began the removal of the inside drop ceiling and all electrical components were removed.

On Tuesday, February 2nd, the rest of the ceiling was removed, and the roof was removed along with the trusses.

On Wednesday, February 3rd, the roofing crew returned and the new trusses were delivered. Crews worked throughout the day placing and securing the new trusses. Within the next few weeks, the new roof will be completed and the old engine room walls will be removed.

We would like to thank Bob Franks Plumbing on Valley Road for the use of his garage for a temporary home for our Engine and Rescue during our renovations!

4/5/10:

While we have not had many updates on the website, much work has been completed. We now have 5 total bays with 7 doors on the building. The stucco on the front of the building is being completely restored and the new bays are taking shape. All concrete has been poured and the attic is roughed in.

This coming week, we will see additional interior electrical work, drywall, and soon the exhaust extraction system will be reinstalled.

5/11/10:

Interior drywall has been completed and paint preparation work has begun. Most of the interior electrical work and heating installation has been completed. The rear porch area, where our new Bingo hall entrance, has been partially completed.

5/28/10:

This week, the exhaust extraction system has been installed and is operational, allowing us to finally place our apparatus back inside the building for the first time in more than 7 months! The blacktop and paving work has begun in the parking lot.

PICTURES CURRENT TO 05/28/10

We are very excited and are in much need of the new addition to our building. Please check back often for more updates.


12/14/09:  Removal of the old parking lot
12/14/09: Removal of the old parking lot
12/14/09
12/14/09
 
12/14/09
12/14/09
12/15/09:  Crew from Simmers Builders arrive to start digging footers
12/15/09: Crew from Simmers Builders arrive to start digging footers
 
12/15/09
12/15/09
12/15/09
12/15/09
 
12/17/09:  Digging of the footers begins
12/17/09: Digging of the footers begins
12/17/09
12/17/09
 
12/17/09
12/17/09
12/21/09
12/21/09
 
12/21/09
12/21/09
12/22/09:  Drainage pipe inserted from the site to the other side of our front driveway
12/22/09: Drainage pipe inserted from the site to the other side of our front driveway
 
12/22/09
12/22/09
12/22/09:  Rescue 44 used to assist with some clean up
12/22/09: Rescue 44 used to assist with some clean up
 
12/22/09
12/22/09
12/22/09
12/22/09
 
12/30/09:  Block arrives and walls started
12/30/09: Block arrives and walls started
12/30/09
12/30/09
 
12/30/09
12/30/09
12/30/09
12/30/09
 
12/30/09:  Block has arrived and is ready for construction
12/30/09: Block has arrived and is ready for construction
12/30/09
12/30/09
 
1/20/10:  More block work is being completed
1/20/10: More block work is being completed
1/20/10
1/20/10
 
1/20/10:  The new East side wall is now taking shape
1/20/10: The new East side wall is now taking shape
1/20/10
1/20/10
 
1/20/10
1/20/10
1/20/10
1/20/10
 
1/25/10:  Steel support beams are put into place
1/25/10: Steel support beams are put into place
1/25/10
1/25/10
 
1/25/10
1/25/10
1/25/10
1/25/10
 
1/25/10:  Vietri Electric marking outlets to remove
1/25/10: Vietri Electric marking outlets to remove
1/25/10
1/25/10
 
1/25/10
1/25/10
1/25/10
1/25/10
 
1/25/10
1/25/10
1/25/10
1/25/10
 
1/25/10
1/25/10
1/26/10
1/26/10
 
1/26/10
1/26/10
1/26/10
1/26/10
 
1/27/10
1/27/10
1/27/10
1/27/10
 
1/27/10
1/27/10
1/27/10
1/27/10
 
2/1/10:  Crews from Simmers Builders and Vietri Electric remove the inside drop ceiling
2/1/10: Crews from Simmers Builders and Vietri Electric remove the inside drop ceiling
2/1/10
2/1/10
 
2/1/10
2/1/10
2/1/10
2/1/10
 
2/1/10
2/1/10
2/1/10
2/1/10
 
2/2/10:  Crews begin removing the roof
2/2/10: Crews begin removing the roof
2/2/2010
2/2/2010
 
2/2/2010
2/2/2010
2/2/2010
2/2/2010
 
2/2/10:  The trusses are being prepared for removal
2/2/10: The trusses are being prepared for removal
2/2/10
2/2/10
 
2/2/10:  Sections of the trusses being removed
2/2/10: Sections of the trusses being removed
2/2/10:  The roof is gone!
2/2/10: The roof is gone!
 
2/2/10
2/2/10
2/2/10
2/2/10
 
2/3/10:  The new trusses are being placed for the new roof
2/3/10: The new trusses are being placed for the new roof
2/3/10
2/3/10
 
2/3/10
2/3/10
2/3/10
2/3/10
 
2/3/10
2/3/10
2/3/10
2/3/10
 
2/3/10
2/3/10
2/3/10
2/3/10
 
2/8/10
2/8/10
2/8/10
2/8/10
 
2/8/10
2/8/10
2/8/10
2/8/10
 
2/8/10
2/8/10
2/8/10
2/8/10
 
2/12/10
2/12/10
2/12/10
2/12/10
 
2/12/10
2/12/10
2/12/10
2/12/10
 
2/12/10
2/12/10
2/12/10
2/12/10
 
2/20/10
2/20/10
2/20/10
2/20/10
 
2/20/10
2/20/10
2/20/10
2/20/10
 
3/2/10
3/2/10
3/2/10
3/2/10
 
3/2/10
3/2/10
3/10/10
3/10/10
 
3/10/10
3/10/10
3/10/10
3/10/10
 
3/11/10
3/11/10
3/11/10
3/11/10
 
3/11/10
3/11/10
3/16/10
3/16/10
 
3/16/10
3/16/10
3/16/10
3/16/10
 
3/16/10
3/16/10
3/16/10
3/16/10
 
3/17/10
3/17/10
3/18/10
3/18/10
 
3/18/10
3/18/10
3/18/10
3/18/10
 
3/18/10
3/18/10
3/18/10
3/18/10
 
3/18/10
3/18/10
3/24/10
3/24/10
 
3/24/10
3/24/10
3/24/10
3/24/10
 
3/24/10
3/24/10
4/5/10
4/5/10
 
New bays, new stucco, new roof!
New bays, new stucco, new roof!
4/5/10
4/5/10
 
4/5/10
4/5/10
4/5/10
4/5/10
 
4/5/10
4/5/10
4/5/10
4/5/10
 
4/9/10
4/9/10
4/9/10
4/9/10
 
4/9/10
4/9/10
4/13/10
4/13/10
 
4/19/10
4/19/10
4/19/10
4/19/10
 
4/19/10
4/19/10
 
4/19/10
4/19/10
4/19/10
4/19/10
 
4/20/10
4/20/10
4/20/10
4/20/10
 
4/21/10
4/21/10
4/21/10
4/21/10
 
4/21/10
4/21/10
4/23/10
4/23/10
 
4/23/10
4/23/10
4/23/10
4/23/10
 
4/23/10
4/23/10
4/28/10
4/28/10
 
4/28/10
4/28/10
4/28/10
4/28/10
 
4/28/10
4/28/10
4/28/10
4/28/10
 
4/28/10
4/28/10
5/3/10
5/3/10
 
5/3/10
5/3/10
5/8/10
5/8/10
 
5/8/10
5/8/10
5/11/10
5/11/10
 
5/13/10
5/13/10
5/13/10
5/13/10
 
5/13/10
5/13/10
5/15/10
5/15/10
 
5/15/10
5/15/10
5/15/10
5/15/10
 
5/15/10
5/15/10
5/19/10
5/19/10
 
5/19/10
5/19/10
5/19/10
5/19/10
 
5/21/10
5/21/10
5/21/10
5/21/10
 
5/21/10
5/21/10
5/21/10
5/21/10
 
5/21/10
5/21/10
5/24/10
5/24/10
 
5/24/10
5/24/10
5/24/10
5/24/10
 
5/25/10
5/25/10
5/25/10
5/25/10
 
5/25/10
5/25/10
5/25/10
5/25/10
 
5/25/10
5/25/10
5/26/10
5/26/10
 
5/26/10
5/26/10
5/27/10
5/27/10
 
5/27/10:  Interior work 90% complete, exterior work 90% complete!
5/27/10: Interior work 90% complete, exterior work 90% complete!
5/27/10
5/27/10
 
5/27/10
5/27/10
5/27/10
5/27/10
 
5/27/10
5/27/10
5/27/10
5/27/10
 
5/27/10
5/27/10
5/27/10
5/27/10
 
Home   |    Guestbook   |    Members E-mail   |    Members Area
Website Designed and Hosted By:
Firehouse Solutions
www.FirehouseSolutions.com
Website Proudly Maintained By:
Westwood Fire Company
1403 Valley Road
Coatesville, PA 19320

Contact Phone Numbers
Copyright © 2005 Firehouse Solutions (A Service of Technology Reflections, Inc.)