New Pumper/Tanker Nearing Completion

 
By EMS Chief John Sly
April 13, 2012
 

On Friday, April 13th, 2012 updated photos were received from our Sales Representative Bob Pursel of Commonwealth Fire Equipment who visited the 4 Guys Manufacturing facility to get updates on our production progress.

The vehicle is now completely painted and compartments are being constructed utilizing plans for equipment mounting and storage.

Over the next 2 weeks, the final assembly process will take place and the vehicle will be outfitted with lighting and accessories.

The anticipated date of completion is within the first two weeks of May.

 
Units: Engine 44-5